‘FULL operational’ na ang Loctob Water Treatment Plant human kini gisugdan sa Richli Water niadto pang Agosto 17.
Pagkakaron, 55Hz ang booster pump nga ilang gigamit kon diin hinay hinay nga paspas apan gi-monitor ang pipeline measure arun malikayan ang kakulian.
“The pipelaying works for the thicker SDR 9 pipeline were completed on August 16. This initiative was undertaken to address the frequent leaks previously caused by high pressure. With this improvement, we are now able to operate more smoothly and efficiently,” suma pa sa pamahayag sa Richli Water.
Sa laing bahin, nag-expansion karon ang Cortes Water Treatment Plan sa ilang Rapid Sand Filtration system.
“The existing RSF was found to have faults in its filter media. To address this issue without implementing a total shutdown of the WTP, we initiated the construction of an additional RSF unit—our third in the facility. The construction is targeted for completion by December 2025. Once completed, we will proceed with the cleaning and repair of the existing filter media, while the newly constructed RSF 3 will sustain continuous operation.”
“Furthermore, if future demand requires additional capacity, Richli Water is fully prepared to expand or construct another Water Treatment Plant. We are committed to ensuring that the water supply keeps pace with consumer needs, and we will not stop until customer demand is fully met.” (Kahlil Lester O. Camba)